Source: Hueiyen News Service
Imphal, January 17 2009:
EXHIBITING HOW much contractor's work sub-standard, the black topping on the road stretch from Kumbi Litan Makhong to Kumbi YP School were found displaced no sooner had the work completed.
The woeful condition of the black topping was found by the media team who went there to cover inaugural function of two water supply schemes with PHED minister TN Haokpi as chief guest.
According to the villagers, the contractor of the work was named as W Inao and villagers have lodged complaints on various occasions but it was in vain as none, the labourers and the contractor comply with the complaints.
The secretary of the Kumbi Setpur Youth Club, Aung in an interaction with the media persons said that if their complaints were not heard and continue as it is in the present mode of black topping, they will force to suspend from further working.
Meanwhile, state PHED minister, TN Haokip today inaugurated two water supply schemes at Chairen and Sagolpat in Kumbi area constructed under the Accelerated Rural Water Supply Scheme.
Local MLA N Mangi also attended the functions.
Giving his speech as chief guest, HN Haokip said even though the schemes were small ones, it will given great benefits to the people of the area.
He also appealed the people to cooperate with the development works taken by the government as it means for the welfare of the people.