Source: The Sangai Express / Addie Chiphang
Ukhrul, March 05:
The Hunphun Katamnao Long ( Ukhrul Students Union) in its strongest term resented the contractor of Ukhrul Town road repairing.
The improvement of the Dist.
HQ town road, under ACA and Bridge at the stretch of 0 to 5.50 Km at the cost of Rs.75 Lacs.
And improvement of the Link road 10.00 Km in length at the cost of Rs.45 Lacs.
However, even the shingling works were not yet begin.
In a firm tone, the student's body said that, the work were below the standard and the guide lines laid down by the ACA, of which it was just a mere eye wash and it is doubtful if the black topping,would last a month.
The sources further add that , there are many left out portions with potholes, and premix carpeting were done only from 86.500 to 89.00 Km.
When this correspondence contacted the E.E.(PWD) Ukhrul, H.Ibohal, he admitted that the works are absolutely unsatisfied and added that the repairing of Ukhrul Town road amounting to Rs.74,98,000/for 0.00 to 5.50 Km but the work has so far covered only 2.670 Km and 2.5 Km has been left out.
The repairing work which starts from the TNL ground and finish at Dungrei Junction are yet to finish.