Questions over commissioning Mapithel Dam

Jajo Themson *

 Maphou Dam, located in Mapithel Hills range, on the bank of Thoubal River :: 5th October 2016
Maphou Dam, located in Mapithel Hills range, on the bank of Thoubal River in October 2016 :: Pix - Lamdamba Oinam



It’s good news for public of Manipur that the long chronic Mapithel dam of Thoubal Multipurpose Project has been officially inaugurated on 27th December, 2020 Sunday. The same was achieved after long exhaustive efforts of the concerned Department IFCD, now Water Resource Department (WRD), Govt. of Manipur to commission the project. The official inauguration program was conducted at Hapta Kangjeibung, Imphal Manipur in the presence of Shri Amit Shah, Union Home Minister and Dr Jitendra Singh, Union Minister of State for DoNER-Independent Charge.

With the Mapithel dam project the project aims to harness three units of power @2.5 MW with gross generation plan of 7.5 MW, drinking water supply @10 MGD to Imphal city and irrigation command @ 33,449 hectares in Thoubal district. Remarkably, it has taken 40 long years of construction, investment made @ over Rs. 1387.85 crore as per latest project cost escalation and final investment clearance from the Niti Aayog, Govt. of India, dated 12th September, 2012, the project caused loss of above 2000 hectares of prime agricultural land, forest, river, homestead areas, ancestral homes and grazing fields in the upstream area.

Besides this, ecosystem and natural environment of the region were either drastically changed or lost. Principal livelihood sources of above 12,000 populace in the upstream and thousands in the downstream region had been sacrificed for the project willingly or unwilling.

Series of successive targets were set for completion of the Mapithel dam project. The 1st commissioning target was-August 1987, the 2nd was-October 1994, the 3rd was-March 2002, the 4th was-March 2007, the 5th was -March 2013, the 6th was-31st March 2015, the 7th was -September 22, 2016, the 8th was – year ending of 2016, the 9th was – 31st March 2017, the 10th was announced on 1st April 2017 and the 11th one was in March, 2018.

Shall we call inauguration of Mapithel dam, success of the project ? Literally, it is a pronouncement of hay-day for general public that a mega development project has been commissioned. It manifests harvest is at hand. Consequently, public have high expectation to enjoy the decades long awaited fruit of the project.

However, there is a big question to be answered. The apparent question is “Is the Mapithel dam project really functioning and harnessing its targeted goals benefitting the public?” Or, is it following the same old stories of immature projects inauguration while no benefit generated ? In a very remarkable way, all the key components of the Mapithel dam project still remain incomplete.

Hydro-power generation plan

One of the main components of the Mapithel dam Project is to install a power house for generating 3 Units of 2.5 MW each of power installed capacity @ 7.5 MW. The actual position of installation of hydro-power generating part is at the initial stage till now. The turbine construction portion is hampered by continuous water logging from leakages at the immediate back wall of the dam.

This may take either at least some more years or inability to construct as the portion is considerably hindered by water leakages. As per reply of the Chief Engineer, IFCD, Manipur on 22nd June 2017, state Govt. is yet to consult to the National Hydro Power Corporation (NHPC) when Irrigation and water supply components will be completed.

Irrigation component

Water supply for irrigation is another key component of the Mapithel dam project. The project is targeted to irrigate 33,449 hectares of irrigation potential area in Thoubal district. However, it was surprising to learn that no remarkable progress of Irrigation canal could be seen during a field visit in May 2017, while the report of the Chief Engineer, IFCD dated 22nd June 2017 claimed to have done 99% seem misinforming.

The proposed Heirok branch canal of Thoubal Left Main canal through prime agricultural land is strongly opposed by the people of Heirok. Villagers are condemning they don’t agree with the Government’s proposal for land acquisition to construct the 100 ft wide canal. Moreover, existence of original targeted irrigation potential area in Thoubal district 40 years back is questionable.

Water Supply component

Supply of drinking water is another major component of the dam. As reported by the staffs of Hyderabad based Company -Coastal Projects Limited, construction of tunnel drill takes one and half year to cover 1185 meters out of 2280 meters since December, 2015. The remaining 1095 meters i.e 49% is likely to take at least another 17/18 months on tunnel drilling.

Moreover, there has been unofficial report that there is severe problem of inability of water to reach the transit reservoir at Chingkheiching from Laikoiching. Thus, it is highly questionable as to whether safe drinking water will reach Imphal city or not as per the status updated by the Chief Engineer, IFCD, Manipur on 22nd June 2017 to complete Water Supply Plan within 4 months.

Poor dam quality

Questions have also been raised on the quality of the construction of the dam. Tumukhong villagers disclosed that laborers randomly filled up the dam with whatever rocks, woods, stones etc. found nearby. Water leakages through 6 major portions were detected at the immediate back wall of the dam since 2015.

The leakages mainly happened at the turbine installing area, Spillway portion and some others at the higher level of the back wall. Addl. Chief Engineer, IFCD in an interview on 10th May 2017 clarified that leakages in the dam is risky if the water seepages become murky with mud. It is undeniable that Mapithel dam is at risk.

Development of multiple earth fissures

Multiple earth fissures and cracks have developed at Maphou/Phayang, Senapati district and Louphong village in Kamjong district. More dreadful situation is several cracks at Maphou Kuki village which was newly resettled.

The most serious case with this incident at Maphou Kuki is either due to cutting of the foot of the mountain on spillway construction and approach road which led to the mountain’s inability to withstand repeated quakes caused due to numerous bomb explosion in the tunnel drilling just at the southern foot of the village or water seepage into rocks beneath the mount, observing high possibility of sliding down the whole mount which can lead to dam collapse. It is highly suspected if the project will be useful in the long run.

Failed CAT Plan

As per the EIA report of the IFCD, Manipur, prepared by the Hydro-Bio-Tech Design Engineers in 2006, there has been side by side of forest areas suffering critical damage due to a plethora of reasons where soil erosion has attained serious proportion. On top of this, no action steps have ever been initiated under Catchment Area Treatment (CAT) plan according to the Forest Department in February 2016 which still remains the same.

The pertinent question here is, “Will the Mapithel dam water reservoir sustain water without regulating the Catchment areas ? The same reminds one of the condition of Singda dam which drastically reduced its expected life span as well as factor of its failure accredited to unprotected catchment areas.

Absence of Holistic Impacts Assessment (HIA)

Blocking of the Yangwui Kong/Thoubal River was done without conducting Holistic/Detailed Impacts Assessment (DIA) covering socio-economy, cultural, livelihood, health, environment & ecology and precautionary measures therewith.

Unwarranted dimensional submergence of residential area, wet paddy field, houses, Churches, school buildings, community hall, homestead areas, low lying forest, animal grazing field and means of transportation had given untold hardship to the affected villagers leading to incredible worsening of their living standard.

Forest Clearance unresolved

Mapithel dam is still marred with acquiring mandatory Forest Clearance from the Central Ministry of Environment and Forest-Climate Change (MoEFCC). Issue of forest diversion @ 595 hectares in respect of Mpithel dam is yet to be resolved.

The National Green Tribunal (NGT), Eastern Bench, Kolkata passed final judgment on 6 December, 2017 in favor of the affected villagers, directing the State respondents to comply with the necessary conditions contained in the Forest Rights (Recognition of Scheduled Tribes and other Traditional Forest Dwellers Right) Act, 2006.

Instead of carrying out the order, the State respondents filed an appeal before the Hon’ble Supreme Court in the early part of 2018. Thus, commissioning of the dam during pendency of forest issue is a violation. The case lies pending before the said Court till date.

Inconclusive R & R program

One of the most important and serious issues of a dam project is Rehabilitation and Resettlement (R & R) program for the affected people. It is the most controversial part which includes social displacement, relocation and rehabilitation of the affected people. There has been no comprehensive conclusion of R & R issue of Mapithel dam till date. Thus, inauguration of the project without solving the RR matter is untimely, inhuman and irrational.

Undermined rights of the indigenous people

The IFCD, Govt. of Manipur even fails to frame up rights safeguard policy in respect of the affected tribal communities of Mapithel dam over their land, forest, river and resources etc. Such traditional rights of indigenous villagers have not been ascertained. This exposes a flagrant violation which undermines the legal framework of India enshrined in Article 338A of the Indian Constitution.

The whole process of conceptual framework, investigation, submission of feasibility report and inception of Mapithel dam construction were done without Free and Prior Informed Consent (FPIC) of the affected communities.

Absence of alternative livelihood arrangement

The WRD, Govt. of Manipur as project agency blatantly failed to arrange alternative livelihood means for the affected villagers, who sacrificed their inter-generational important land, river, forest and resources that sustained their lives.

The massive inundation unleashed adverse impacts on the livelihood and survival of villagers losing food sovereignty in the affected area. At the same time, community people living in the downstream villages suffer from shortage of water, curtailing livelihood such as fishing, agriculture and seasonal collection of sand and stone from the River.

Conclusion

It is fine the Mapithel dam project has been commissioned now even inspite of numerous hue and cry of the public in general and the affected villagers in particular. However, in addition to irrationality of commissioning this project like discussed above, there is still another big question mark regarding responsibility and accountability of the project.

Who is taking responsibility for completion of the immature project parts while the project is already commissioned ? Who will account for success or failure of the dam project ? It is highly suspected Mapithel dam follows the same living examples of previous dams which were left unattended after inauguration.

Or, is Mapithel dam creating another story of previously failed dam projects like Dolaithabi Barrage commissioned in August 2019 which remained fruitless, total flopped Khoupum dam in Tamenglong, rusted Singda dam and gross ineffectual Khuga dam in Churachandpur district which were either left abandoned in complete futility or marooned after commissioning them.

Crores of Rupees have been spent, consumed 40 years in its construction, indigenous villagers have surrendered their right over their invaluable land, forest, river, resources loving ancestral homes for the project, their principal livelihood sources have been sacrificed, the dam had caused unfathomed dimension of hardship to land donors and still they don’t have hope of betterment in the future.

What is expected by the general public is not the name sake commissioning of project, but the positive outcomes. Making development projects as a gamble for getting political mileage as well as construing achievement records ought not be appreciated by public.

If it is not functioning and harnessing the targeted benefits, why should public money be wasted and people made to suffer for such unsustainable project ! It is quite irrational and unfair that the affected people face undue suffering and a devastated environment for the project like Mapithel dam which is not functioning.

If it is not serious, let the Yangwui Kong/Thoubal River return to its natural flow. These are the core concerns why the affected villagers along with the right wings have been relentlessly striving since 1990s.

It is right to assert that Mapithel dam of Thoubal Multipurpose Project has become another history of White Elephant project installed in Manipur. Time has come, public realise the unsustainability of such dams and hydropower projects from the past and present Mapithel case.

Moreover, decommissioning all the unsustainable futile dams projects including Mapithel dam would be the right solution towards sustainable and development justice in the State.


* Jajo Themson wrote this article for The Sangai Express
The writer may be reached at thmsontezonge(AT)gmail(DOT)com
This article was webcasted on January 22 2021.



* Comments posted by users in this discussion thread and other parts of this site are opinions of the individuals posting them (whose user ID is displayed alongside) and not the views of e-pao.net. We strongly recommend that users exercise responsibility, sensitivity and caution over language while writing your opinions which will be seen and read by other users. Please read a complete Guideline on using comments on this website.




LATEST IN E-PAO.NET
  • '365 Days of Chin-Kuki Aggression' : Gallery
  • Violence in Manipur 2023-2024 : Timeline
  • Renaissance of politics in our youth
  • TB & tobacco co-epidemics in Indonesia
  • The Power of Poppy - 29 :: Poem
  • Advanced Charging Infrastructure in NE
  • Lessons learnt in the last one year
  • True colour of politics
  • World Heritage Day @ MU : Gallery
  • "ST status for Meetei" at Kakwa
  • Joint Combing Operations in Jiribam
  • Reboot PSUs for jobs: Task for new Govt
  • Ayurvedic remedies to keep healthy eyes
  • May 3, 2023 to May 3, 2024
  • One year of crisis, and what next ?
  • Scientist of Manipur: Nongmaithem Rajmuhon
  • Whither social justice & work for women?
  • Taiwan to enhancing economic ties with India
  • Integrated Farming Systems for farmers #2
  • Athoubasingi Numit #2 : Gallery
  • Privilege trap of While Male Meitei
  • Crop/animal for higher productivity in NE #4
  • 'Chizami Model' working in Gujarat ?
  • Racing towards the one year mark
  • On misattribution & falsifying history
  • Nupi Landa Thaunaphabishing #15 :: Book
  • May Calendar for Year 2024 : Tools
  • 12th World Bamboo Congress at Taiwan
  • Complex dance of democracy in Manipur
  • "ST status for Meetei" at Pangaltabi
  • Integrated Farming Systems for farmers #1
  • Showing ugly face of muscle power
  • Spare the rod, spoil the monster
  • Descent of Radha-Krishna #31: Download
  • Socio-Historical analysis on Ethnic Conflict
  • "ST status for Meetei" at Langmeidong
  • Ngangbam Dipapati- Gold @European Cup
  • Crop/animal for higher productivity in NE #3
  • Fresh surge in violence
  • The real culprit
  • National Science Teacher workshop
  • Livelihood Disaster in Mapithel Region
  • Condemns Killing of CRPF Personnel
  • "ST status for Meetei" at Manipur College
  • Huidrom Oliviya: Silver @Cadet European Cup
  • Election: Runner-up may spoil the joy
  • Scientists of Manipur : Laishram Ladu Singh
  • Imphal Ring Road Project to Transform
  • Crop/animal for higher productivity in NE #2
  • The Power of Poppy - 28 :: Poem
  • Condemned unabated illegal taxation
  • Watermelon : Super nutritious summer fruit
  • People have spoken, Manipur has voted
  • Skirting around core issues
  • Lok Sabha polls in Manipur #2 : Gallery
  • The Taj Mahal that bans Lovers !
  • Importance of bees !
  • Massive hailstorm in Jiribam
  • The messiah of hapless children
  • Attack on fuel tankers & blasting bridge
  • Blame it on Meetei
  • The Happiness Code : Download
  • NH-2 Bridge bombed @Sapermeina : Gallery
  • Crop/animal for higher productivity in NE #1
  • Training Programme under SPARK concluded
  • Why environment control is so difficult
  • 4th Foundation Day- Young Minds Collective
  • All set for second phase poll
  • The Nongsaba phenomenon
  • Khongjom Day @Khebaching #1 : Gallery
  • India's responsibility to end Manipur violence
  • Migrant worker could access TB services only
  • Importance of reading magazines as student
  • SHG pioneering agricultural innovation
  • Nearing the one year mark
  • The enemy within
  • Id-ul-Fitr @Hatta #2 : Gallery
  • Workshop @ NSU Manipur : Gallery
  • 15th Manipur State Film Awards 2023
  • "ST status for Meetei" at Panthoibi Shanglen
  • GSDP doubles, health shines
  • Vote has been cast, repoll held
  • Two faces of democracy
  • Laurels for Scientist Ngangkham Nimai
  • Crime against women in Manipur
  • "ST status for Meetei" at Sugnu
  • Creativity & innovation for vibrant career
  • 4th Foundation Day of YMC
  • Racing towards one year mark
  • Prophetic words, indeed
  • Nupi Landa Thaunaphabishing #14 :: Book
  • 174th Anniv Maharaj Narasingh #1 : Gallery
  • Ensuring Fair Voting in Hills of Manipur
  • Dr Irengbam Mohendra's latest book :: Rvw
  • NDA has the advantage in both
  • Lok Sabha polls in Manipur #1 : Gallery
  • L Rup's Robot 'Kangleinganbi' in Manipuri
  • Art- means of connecting hearts in Manipur
  • Is it Living Alive or Living Death ? :: Poem
  • Rabies - A preventable zoonotic disease
  • April 19, 2024: The blackest day of all
  • Ugly turns on voting day
  • Children Camp @JNMDA Imphal #2 : Gallery
  • The chasm between TB & HIV continues
  • Parliament and its Members
  • Kimchi for health and glowing skin
  • LS election with a difference
  • To vote, or not to vote ?
  • Sajibu Cheiraoba Chak Katpa #2 : Gallery
  • "ST status for Meetei" at Lamjao, Kakching
  • The Power of Poppy - 27 :: Poem
  • Mother Language based education essential
  • Modi's warriors wear regional hats
  • Nest Asia promoting Northeastern Cuisine
  • Now look beyond LS poll
  • The rot in the system
  • Scientists of Manipur : Laitonjam Warjeet
  • Community seed bank @Umathel : Gallery
  • 10 candidates cracked Civil Services Exam
  • Milk of Paradise: History of Opium : Rvw
  • How plastics find their way into our bodies
  • Condemning attack on Trucks along NH-37
  • Cong looking to buck the trend
  • Saving Manipur
  • Sajibu Cheiraoba: 1 occasion, 2 narratives #2
  • Election Duty :: Travellog
  • 1st Nagas' Meet in Punjab
  • How to select right MP to represent Manipur
  • "ST status for Meetei" at Tejpur
  • Bats are Keystone species for the Planet
  • The '15 days' conundrum
  • Free but not so fair
  • Descent of Radha-Krishna #30: Download
  • Before You Vote : My Rumbling Thoughts
  • "ST status for Meetei" at Kakching
  • Meiraba wins All India Sr tournament
  • Finding light in dark through my daughter
  • Navigating life's unreasonable expectations
  • Test of people's character
  • BJP's election manifesto
  • Athoubasingi Numit #1 : Gallery
  • Black rice & Glycemic Index
  • What Nadda should speak at Dimapur rally
  • Open Letter to CM Office Manipur
  • Meghalaya unveils Strawberry festival
  • Benefits of maths newspapers for students
  • Id-ul-Fitr @Hatta #1 : Gallery
  • Are you a good person ?
  • Physics Academy of NE : Executive Body
  • "ST status for Meetei" at Moirang
  • Cherrapunji Eastern Craft Gin launched
  • Cong on cautious path
  • Botox for Hair
  • Posers voters should raise now
  • The lull before the storm
  • 80th Anniv- Battle of Kanglatongbi @UK
  • Vir Chakra Ngangom Joydutta's bust unveiled
  • Hun - Thadou Cultural Festival : Gallery
  • "ST status for Meetei" at Singjamei
  • Election Eclipses: Ballad of Battle & Loss
  • Our voices are equal at the ballot box
  • Scientists of Manipur : Ngangkham Nimai
  • Urgent Call for Solidarity in Manipur
  • Meitei Nongsha #2 :: An Artwork
  • "ST status for Meetei" at Waikhong
  • About NPF-BJP-NPP alliance & why ?
  • World Veterinary Day, 2024
  • The heavy stake behind the LS polls
  • The politics of lying & deception
  • Sajibu Cheiraoba Chak Katpa #1 : Gallery
  • Hun-Thadou Cultural Fest @ Delhi: Report
  • Appeal to Parties & Candidates
  • "ST status for Meetei" at Wangoo
  • Establishment of community seed bank
  • Awareness Programme on new Criminal Laws
  • Make a right choice at the Lok Sabha election
  • Sajibu Cheiraoba: 1 occasion, 2 narratives #1
  • RIST talk-58 : Support systems of elderly
  • "ST status for Meetei" at Hiyanglam
  • Vote, do not boycott !
  • Lok Sabha election: A new dawn in politics ?
  • IIT-Guwahati Half Marathon report
  • Taking ST demand to the election ring
  • Lesson to be learnt from across border
  • Mirabai: Poised for Paris Olympics
  • Legal position for protection of environment
  • "ST status for Meetei" at Keisamthong
  • Heterocyclic compound & biochemical science
  • Inner, torn between two lovers
  • Certification Music Therapy Workshop
  • NOTA as a choice
  • Caesar's wife must be above suspicion
  • Descent of Radha-Krishna #29: Download
  • World Health Day 2024
  • "ST status for Meetei" at Pangantabi
  • The Power of Poppy - 26 :: Poem
  • Fulbright Fellowship Outreach at Arunachal
  • Id-ul Fitr da namaz nattana..
  • Nupi Landa Thaunaphabishing #13 :: Book
  • Lok Sabha election is coming, be prepared
  • 6th Hun-Thadou Cultural Festival
  • Let There Be Free & Fair Election
  • "ST status for Meetei" at Lamlong
  • Science magazines are important for student
  • Interesting choice of candidates
  • The power of We, the voters
  • Inspirations from Scientists of Manipur #1
  • The Case for Amendment of Article 371-C
  • Meitei Nongsha #1 :: Artwork
  • Link between forest & conflict in Manipur
  • Final Call for Application MFA - Phase-2
  • ST for Meiteis call before elections
  • Passing the buck
  • Beating of the Retreat #1 : Gallery
  • Life of our Lives in Ethnic Strife Era! :: Poem
  • IIT-Guwahati annual Half Marathon
  • Follow up: European Parliament on Manipur
  • Yoga & Kegel exercise: Pelvic floor workout
  • Opting for the NOTA button
  • Yearning of the displaced people
  • Kenedy Khuman (Singer) : Gallery
  • 5th NE Women's Peace Congregation
  • World Autism Awareness Day 2024
  • Election fever grips Manipur despite unrest
  • Looking for a decent election hustings
  • Clock ticking towards voting day
  • An exemplary directive
  • Children Camp @JNMDA Imphal #1 : Gallery
  • Memo to Election Commission of India
  • Easter & Holi echo in Nilgiris
  • Holiday Camp for children at JNMDA, Imphal
  • Zero waste is our moral responsibility
  • Elections & loyalty vis-a-vis Manipur crisis
  • Show of strength without unity
  • Yaoshang Pichakari #2 : Gallery
  • Panthoi Chanu : 1st to play in Australia
  • Intensive labs in film preservation
  • Building bridges with books
  • Need of the hour: Political maturity
  • Accepting defeat before the election
  • Descent of Radha-Krishna #28: Download
  • Natural packaging from bamboo : Gallery
  • Yaoshang Mei Thaba #2 : Gallery
  • Manipur's original Ponies : Gallery
  • Lamta Thangja @ Imphal : Gallery
  • Meira Paibis of Manipur
  • North East Film Festival #2 : Gallery
  • Students @ Class X Exam : Gallery
  • Saroi Khangba @ Kangla : Gallery
  • Protest for scrapping SoO #2 :Gallery
  • Shopping List for Shivaratri : Gallery
  • N Tombi Equestrian C'ships #1 : Gallery
  • Featured Front Page Photo 2024 #1: Gallery
  • Radio E-pao: Manipuri Film OST (130+ song)
  • Save Manipur : Protest [Feb 15] #3 : Gallery
  • Naorem Roshibina- Wushu Medallist : Gallery
  • GHOST of PEACE :: Download Booklet
  • List of Kings of Manipur: 33 - 1984 AD