E-Pao! Education - Tipaimukh Dam Is A Geotectonic Blunder Of International Dimensions?

Tipaimukh Dam Is A Geotectonic Blunder Of International Dimensions?
- Part 2 -

By: Dr. Debabrata Roy Laifungbam / Dr. Soibam Ibotombi *



Tipaimukh Dam/Cachar Plain Irrigation Project: A Complicated International Disaster
Scenario for Bangladesh


The scenario and consequences of a Tipaimukh Dam-break has not been thoroughly studied. NEEPCO has yet to complete a basic scientifically sound environment impact assessment even though it is geared up to start construction after having opened international bidding for Engineering, Procurement and Construction (EPC). Such a study has to be conducted by international as well as national dam-safety experts as the impacts of a dam-break will have both severe upstream and downstream effects.

However, the downstream effects of a Tipaimukh Dam-break have been studied by the Government of Bangladesh since 1992-94. In its Flood Action Plan 6 (FAP 6) as part of the North Eastern Regional Water Management Plan of Bangladesh, the scenario of a dam failure at Tipaimukh Dam project was investigated by international hydraulic and environmental experts in the context of a comprehensive flood action plan for Sylhet District.

India is also planning a major Cachar Plain Irrigation Project downstream of the dam. Bangladesh already knew a fact that we in Manipur do not know still. Surprisingly, for the people of Manipur, the Tipaimukh project is not the only project at the drawing board on the Barak River. This means that water released from the dam reservoir will be further diverted for the irrigation project planned in Cachar District, contrary to NEEPCO's recent claims.

FAP 6 had a Future Without Plan (FWO) component that looks at a dam-break scenario with minimally adequate project description available through the Joint Rivers Commission (Indo-Bangladesh). Bangladesh has pending issues with the Government of India with regard to the dam that includes the effects of flow regulation. Regulation of the Barak's flow by Tipaimukh Dam would provide India with the opportunity to irrigate the Cachar Plain; this India proposes to do.

Since the Cachar Plain Irrigation plan involves the loss of water, it is a matter of great concern to Bangladesh particularly its North Eastern Region as no statement is available how much water Indian intends to take from this scheme. For the purposes of the FAP 6 study it was assumed that the total depth of irrigation water to be applied is 1 M and that the water is diverted on a continuous basis during the six dry months (November through April).

A dam-break scenario must be studied by dam safety specialists. It is very doubtful whether NEEPCO or any other agency has conducted such a study. According to the Bangladesh study, the risk that the Tipaimukh Dam poses for Bangladesh is extremely significant for the Meghna River system (including the Surma and Kushiyara Rivers of Sylhet).

The study recognises that the region is known to be vulnerable to earthquakes. These events, though relatively rare are extreme in intensity, and can reverse existing morphologic trends and even induce re-configuration of the drainage system.

The likelihood that during 1991-2015 the region would experience an earthquake of magnitude 7.6 (similar to the 8 July 1918 event with its epicenter at Srimangal of magnitude 7.6, return period of 30 to 50 years) is between 40 and 60%; of magnitude 8.7 (similar to the 12 June 1897 event with its epicenter at the Shillong Plateau with magnitude 8.7, the largest on record, return period of 300 to 1000 years) is perhaps 2 to 5%, assuming the events are random and can be described with a simple binomial probability model.

On past evidence, river channels and sedimentation patterns in the Northeast Region may be subject to major disruptions following a severe seismic event. During past earthquakes, instances of ground liquefaction, landsliding, rapid subsidence, collapse of river banks, and changes to river courses have been documented (District Gazetteer, 1917). The effects of earthquakes along the Brahmaputra River were described in 1899:

"Strong ground shaking triggers liquefaction of river cross-sections in a few seconds; underwater slopes slide towards the stream axis, the bottom of the river heaves, and the banks become lowered; water immediately starts to rise and overflows the banks and adjacent zones where infilling of the channels takes place. Natural sills form, causing temporary lakes to develop; channels gradually re-open by scouring where currents are strong enough, and consequently water levels decrease.

Where channels remain blocked, streams desert their old channels to form new ones; and in subsequent years, the huge amounts of sediment poured into the river as a result of the earthquake gradually moves downstream. Sediment transport is higher than previously and siltation conditions are therefore modified.

Earthquakes are believed to have also induced landsliding and slope failures in headwater catchments in the Shillong Plateau, which could greatly increase the amount of sediment supplied to the region for long periods of time. Joglekar (1971) described apparent impacts of major earthquakes on the upper Brahmaputra in Assam, India. After the severe earthquakes of 1947 and 1950, the bed level near Dibrugarh rose substantially. Between 1947 and 1951, low water levels rose by as much as three to four metres; thereafter they were steady.

Dam Failure

This risk is however a significant issue relating to future environmental management of the Northeast Region water system of Bangladesh.

A dambreak is a catastrophic failure of a dam which results in the sudden draining of the reservoir and a severe flood wave that causes destruction and in many cases death downstream. While such failures are rare and are not planned they have happened to dams, large and small, from time to time. The International Commission on Large Dams (ICOLD) has identified 164 major dam failures in the period from 1900 to 1965.

With respect to the safety of the proposed Tipaimukh Dam, hydraulic and environmental specialists opine that well-designed and constructed rockfill dams are perhaps the safest type for large heights (Tipaimukh would be among the largest of such dams in the world), but local circumstances may be much more important in this respect than dam type.

Two examples illustrate the types of failures that have been reported. The most famous, the Teton Dam in the United States was a 90 m high earth-fill dam which failed in 1.25 hours. The flood wave which was released had a peak discharge of 65,000 m3 s-1 at the dam and a height of 20 m high in the downstream canyon. The Huaccoto Dam in Peru was 170 m high, similar to the Tipaimukh Dam; it failed over 48 hours due to a natural landslide in the reservoir.

Generally, a flood wave travels downstream at a rate in the order of 10 km hr-1 although velocities as high as 30 km hr-1 have been reported near failure sites. From these wave velocities, it would appear that the initial flood wave could travel the 200 km distance from Tipaimukh Dam site to the eastern limit of Bangladesh within 24 hours having a height of perhaps 5 m. Peak flooding would occur some 24 to 48 hours later. High inflows would persist for ten days or longer and the flooded area would likely take several weeks to drain.

The Tipaimukh reservoir is huge (15,000 Mm3) compared with experience reported in the literature. In the event of a significant unplanned discharge, the river system in Bangladesh would respond (drain) rather slowly, as characterized by the outflow rate relative to the floodplain storage volume), such that most of the water released would remain ponded over the Northeast Region for some time. Assuming a release volume of 10 Mm3 and a ponded area of 100 km2, the depth of flooding would be an average of 1.0 m above the normal flood level.

There will be first an imperative need for Bangladesh and India to cooperate in formulating and implementing risk management measures if the Tipaimukh Dam as presently designed should be constructed. A wide range of risk management measures are normally undertaken, including: regular inspections by independent engineering teams, instrumentation and plans for warning downstream populations of deteriorating conditions of a dam, evacuation plans, and so on. As and when India's plans proceed, there will be a clear need for Bangladesh to avail itself of expert technical assistance from dam safety specialists experienced with very large dam/reservoir systems and trans-border risk management.

For illustrative purposes only, the Bangladesh study modeled flood waves for a test case of an instantaneous failure, 50 m wide extending to 100 m below the crest of the dam. Discharge and water level hydrographs were presented for three locations: at the exit from the mountain valley (km 80), at Silchar (in the middle of the Cachar plain, km 140) and at Amalshid (km 200).

It was forecast that substantial attenuation of the flood wave would occur upstream of Amalshid and that the flood wave at Amalshid would be a long-duration event. Depending on the breech geometry and peak discharge, the flood peak would occur at Amalshid approximately 2 to 3 days after the dam break had occurred and flooding would continue for ten days or more. The flood levels at Amalshid would rise to approximately 25 m PWD (peak water discharge), which is at approximately 8 m above the floodplain level. This flood level depends on the boundary assumptions made and could vary depending on floodplain conveyance.

Socio-Economic Aspects: "An Electric Bulb from every Tree"

As per the technical report of the NEEPCO (1998), the dam will have a firm generation of 401.25MW only implying that 401.25MW of power only will be generated regularly, and this is the best scenario. And again as per the past Central Government formula, the Government of Manipur (GOM) will get only 12% of 401.25 i.e. 40-43MW free (sharing with Mizoram where 90% is claimed by Manipur state but this is subject to Government of India set norms which has changed from time to time; it has been revised since).

In order to get this 40-43MW of power, the State will be loosing around 293.56Km2 under submergence of reservoir water which includes 4760ha of gardens, 2053ha of rice cultivable land, 178.21Km2 of total 7251.36Km2 of forest land beside affecting a numbers of villages (15+90). Let us introspect as well as retrospect the case of Tipaimukh dam in comparison with the Loktak Hydro Electric Project and analyze the possible implications in the next 50 years hence especially for the natural resources that will be deprived of the state.

When Loktak project was initiated in the late 1960's - the tall claims made by the authority/government were: thousands of hectares of cultivable land will be generated by draining water of Loktak lake to Leimatak river, price of 1 unit of power will be only 5 paise, the installed capacity of 105MW is 10 times more than the power what the State requires and there will be no power problem for the next 50 years or so, etc.

Now it is over 20 years of commissioning of the project - thousands of cultivable land have been submerged under the lake (reservoir) water contrary to what they claimed, 50-70 paise was price of 1 unit of power at the time of commission, power supply is at its worst nowadays and likely to worsen, which every citizen knows; and rehabilitation and compensation issues are yet to be settled at the Gauhati High Court.

And besides, a range of grave environmental and ecological problems especially of the Loktak Lake threatens this internationally important wetland's very existence along with the Keibul Lamjao National Park, with ecological damage to the entire Imphal Valley and the catchment areas. The State gets about 6-10MW of free power intermittently from the Loktak Hydro Project. The question is whether it is sufficient to compensate the economic, natural resources and environmental loss which the State bears presently?

Now let us examine the possible implications of the Tipaimukh project in a similar manner. As pointed out above, the 293.56Km2 of submerged area consists of 5760ha and 2053ha of garden and cultivable lands respectively. These figures, the author believes, are far underestimated because at present, less than 50% of arable and cultivable lands in the Barak river beds are utilized due to thin population of the region, which will be possibly utilized in the next 50 years due to population increase. So approximately a total of about 15,626ha (11520ha + 4106ha) of cultivable land will be lost.

Again, although 178.21Km2 of the total forest area will be permanently submerged under water, practically the natural resources of a much larger forest area will be unavailable permanently to the State. Net Present Value levy for forest land conversion to non-forestry use as per the Supreme Court directives would also make the project economically unviable, as claimed by NEEPCO on 28t January 2006 (Tipaimukh Multipurpose project tariff increases by 67 paisa/unit on this account of NPV) in its submission to the Supreme Court's Expert Committee.

Compensatory Afforestation Programmes (CAP) will take over large tracts of other categories of forested lands besides Reserve Forests as well, but most of these programmes will never be implemented. After completion of the project, the project authority will claim that depletion of forest and other natural resources in the nearby catchment area will increase siltation in the reservoir leading to the reduction in storage capacity of the reservoir. This, in turn, will reduce the generation capability of the power plant and so on.

The same was true in the case Loktak project where the lake water level is to be maintained as a reservoir in order to generate electricity, submerging thousands of cultivable land contrary to what the authority claimed in the beginning. So the question that can be raised is whether it will be a wise policy, in the long run, to surrender such a huge natural resources just for 40-43MW of free power. This is a huge question, no doubt, to ponder upon.

Discussion and Conclusion

Structural and tectonic setting, plate kinematics and interaction as well as seismic potential of Manipur state and the serious implications for the entire region's existing geomorphologic trends and even induce re-configuration of the drainage system amount to scientific and technical objections to the construction of a huge dam of the magnitude proposed in case of the Tipaimukh dam. Because, such a outmoded design dam may have the potential risk of a great disaster, killing hundreds and thousands of lives, and causing generational incalculable losses to future economic options, livelihoods and cultures.

So, the government must rethink about the construction of such a huge dam. Instead, it is advisable to construct relatively smaller projects with improved modern designs in order to scale down the magnitude of possible disaster since earthquake prediction and prevention is beyond human capability. It would be wiser and economically more sustainable to consider smaller dams or Run-of-the-River (RoR) schemes with an objective to reduce human induced disaster, and save the river.

Construction of smaller projects not only will tone down the magnitude of the possible human induced disaster but also will provide balanced sustainable development avenues for various regions of the State as well as minimize the environmental and ecological instability. In the meantime, Government of Manipur also should reassess all the power projects especially in terms of its operational efficiency and potentiality instead of simply waiting for a mere 40-43MW free power from Tipaimukh project which could last as long as 20-25 years.

For instance, the expected maximum head (difference between reservoir water level and power generation unit) is about 160m in the case of Tipaimukh project while in the case of Loktak Lake the head is about 269m which is approximately 100m more than that of the proposed Tipaimukh project. But such a tremendous head is wasted just to generate a variable 40-80MW of power only. This is nothing but sheer wasting of huge natural resources by severely underutilizing the immense potential. So, the potential of the installed Loktak project should be fully harnessed by Manipur after reassessing and renovating with an objective of enhancing its efficacy and benefit to the State while the project exists.

In conclusion, let us not waste and surrender our huge natural resources just for 40-43MW of power, and let us introspect, learn through mistakes of the past and rectify ourselves than repeating it. Because a wrong decision of ours will cost heavily on our future generation who will, otherwise, never forgive us. Let us remember popular Native American proverb which says, "The frog does not drink up the pond in which he lives."


Dr. Debabrata Roy Laifungbam is the Director, CORE, Manipur. Dr. Soibam Ibotombi is from the Dept. of Earth Sciences, Manipur University. This is their first contribution to e-pao.net . You can contact CORE (Centre for Organisation Research & Education) at http://www.coremanipur.org/


* Comments posted by users in this discussion thread and other parts of this site are opinions of the individuals posting them (whose user ID is displayed alongside) and not the views of e-pao.net. We strongly recommend that users exercise responsibility, sensitivity and caution over language while writing your opinions which will be seen and read by other users. Please read a complete Guideline on using comments on this website.




LATEST IN E-PAO.NET
  • Shivaratri Shopping List #2 : Gallery
  • Pherzawl - a dying District! ?
  • Indo-Naga & other peace talks #2
  • Spotted Deer - Living with Natural Habitat
  • Northeast Fiesta at Jalandhar : Report
  • Environmental Sciences as career option
  • Serou: A microcosm of mosaic Manipur
  • 3 North East States to get DNA Testing
  • Protest against SC verdict on adultery
  • Mirabai misses bronze by a whisker
  • Post poll scenario in Manipur
  • Tributes to PLA killed #2 : Gallery
  • Romance of insurgency in 1970s #1
  • Earth Day 2019
  • Easter is a Day of Hope for all ...
  • Hide-and-seek in the Sky :: Poem
  • St Mary's Church: The 1st Anglican Church
  • Breaking the barrier
  • A talk with Ajit Ningthouja :: eRang
  • Realisation Day; Echoes the wake up call
  • Xavier Rutsa & Limatemsu Jamir
  • Revisiting Palm Sunday: Reflections..
  • Iceland - most safest & peaceful place
  • Easy fixes for summer hair problems
  • An evening of extreme shame !
  • Revisiting reality
  • LS : Voting for Inner : Gallery
  • Ahingbi, Chareinu :: eMing
  • Thang Ta @Sangai Festival #4: Gallery
  • The current status of Naga-Kuki relation #1
  • Traditional warfare technique of NE native #1
  • Cry Of A Dying River #72 :: Poem
  • Looking forward to May 23
  • Judgment day
  • Meekap Thokpa Numit #1 : Gallery
  • CC Meet Final: NEROCA Vs SU #2: Gallery
  • Floriculture : A booming industry in Mao
  • Positivity is the soul of life
  • Basic health competency by patients
  • Inner Line Permit (ILP) Demand :: Timeline
  • 7th Woodpecker International Film Festival
  • Cracking the repoll whip in Outer
  • Dirty game is a threat to Democracy
  • Ibendhou Kounu Haraoba #2: Gallery
  • Indo-Naga & other peace talks #1
  • Civil Society Forum Manifesto for Election
  • Life and Me :: Poem
  • The Killing Fields 2013-18 : News Timeline
  • Election jamboree & voters bonanza
  • Suspension Order for 7 MLAs : NPF
  • Chin Woman Dies after Tatmadaw Bomb
  • A reference to the party in power
  • An idea without fear
  • Sajibu Cheiraoba at Mysore #2: Gallery
  • Artillery Regiment in Battle of Imphal
  • Appraisal on LS election (Outer) #2
  • Minimum Income Guarantee is a promise
  • Northeast Fiesta 2019 at Jalandhar
  • Cyber Security - the need of the hour
  • Sunset Unplugged, Agartala: Event Report
  • Reality of casting vote in Outer PC
  • Real face of Indian election
  • Tributes to PLA killed #1 : Gallery
  • Khomlen Manglanda : Play synopsis
  • Download: Meetei Mayek Keyboard
  • Voting (PC) @ Kangpokpi #3: Gallery
  • Letter from a river most polluted
  • Truth commission in Manipur needed..
  • Vacancy at Makok Tech, Bishnupur
  • Cheirao Chingkaba #2 : Gallery
  • The sky is the SIYOM of the stars
  • An introspection of roots of AFSPA
  • A note on Cheiraoba ..
  • A well-known paradox :: Poem
  • The saga of EVMs
  • Festival of Democracy hypes
  • 14 girls sold to persons in Saudi Arabia
  • Took up boxing after watching Ali- Mary
  • Sajibu Cheiraoba at Mysore #1: Gallery
  • Mittong Khunou: The Battle Honour of INA
  • A Lifeline for the Assamese
  • Multiple posts at PiCaSoid, Imphal
  • NE Annual day of CNESPR , JMI
  • Essential summer travel tips
  • Discussion : Myanmar's Democratization
  • Violating election model code of conduct
  • Catapulting AFSPA in the limelight
  • Revisiting CAB issue
  • Voting (PC) @ Kangpokpi #2: Gallery
  • Voting (PC) @ Kangpokpi #1: Gallery
  • Bloody Phanek at Paris Film Festival
  • Homoeopathy, a revolutionary science
  • The goodness of good fate does not smile..
  • Outer Constituency has voted
  • Helpless indignation
  • CC Meet Final: NEROCA Vs SU #1: Gallery
  • Yengkhom Roma : Lifetime Award
  • Appraisal on Lok Sabha election (Outer) #1
  • Cyber Crimes - Crimes by finger tips
  • Research Support Officer @ Amethyst
  • Condemns militarization of NEHU Campus
  • Shadow of CAB on Lok Sabha elections
  • "CAB" Factor Faded
  • Thabal Chongba @Khurai : Gallery
  • Military Sociology: Present, Past & Future
  • Know your MP - Election 2019
  • Dirty Dancing :: Poem
  • Democracy needs time for good admin
  • Travel at U-Factor
  • Shadow of NSCN (IM) in Outer PC
  • The great escape
  • Arambai Exhibition Show : Gallery
  • View of Premier State College Senior Assn
  • Distant One :: Poem
  • The hysteria of a first time voter
  • Course in Folkloristics & Semiotics
  • NDPP is 'Entertainment Govt' : Zeliang
  • On issue of "Letters signed by Neiphiu Rio"
  • The visit of PM Modi
  • If BJP win, people of Manipur support CAB
  • Cheirao Chingkaba #1 : Gallery
  • sekeN heN :: Seireng
  • Yangnu Golmei : Sangeetbhusan 2018
  • Victimizing only the Women & Children
  • Lest The North-East Fall Asleep
  • Naga Peace Process :: News Timeline
  • Driving a dangerous feat on Indian roads
  • Need to be democratic in a democracy
  • Cheiraoba Chak Katpa #1 : Gallery
  • Selfie da track :: e-pao Radio
  • Demand for ILP :: Articles/Photos...
  • The legend of the Laiyyars : Election tale
  • Sports for peace & development
  • What is peace ?
  • Rongali : Celebration of Assam & NE
  • Manipuris celebrate New Year
  • Imphal security beefed for Modi's visit
  • Sajibu Nongma Panba Shopping: Gallery
  • Sajibu Cheiraoba: Ritual festival of Meiteis
  • Sajibu Cheiraoba Meitei New Year Day
  • Stop War with Nature :: Artwork
  • Cry of a Dying River - 71 :: Poem
  • Pulmonary Valve Balloon dilatation
  • Supping with an ally of the foe
  • Deflected focus: The dress debacle
  • Nipalsuba Mapok #2 : Gallery
  • Running for LS polls: The candidate
  • Gift :: Poem
  • Architect/Architectural Designer @R-Square
  • Little things that help to enhance beauty
  • Congress Manifesto for Repeal AFSPA
  • Social Media - a boon or a curse?
  • Anti-CAB stand: Interesting take from PRISM
  • AFSPA on Congress Manifesto
  • Bamboo Cooking Competition #1 : Gallery
  • April Calendar for Year 2019 :: Tools
  • Yaoshang Sports @Keishampat #2 : Gallery
  • First Wave Feminism
  • JRF wanted at NERIST, Arunachal [Upd]
  • Cheiraoba Thabal 2019 at Bangalore
  • NPF to support Congress on issue based
  • Jyotishmita to represent Assam in Miss India
  • Paothang : Newsletter from Pune
  • Eyeing votes with promise on AFSPA
  • Together let's save the future
  • Shirarakhong Village, Ukhrul :: 360 View
  • Journey into Nature of Human Culture #4
  • Candidate accommodation at Aligarh
  • The globe is in your fist
  • Heartless :: Poem
  • Condemn Killing of Manjur Ahmed
  • Indifference bordering on arrogance
  • Modi's visit: Will it restored BJP image?
  • Yaoshang Halankar #1 : Gallery
  • No Budget at International Mime Festival
  • In defence of the "Meira Paibis"
  • Post-Doctoral fellow @ NEIST, Jorhat
  • Attributes for vibrant career #2
  • Against Custodian Killing of Manjur Ahmed
  • Revamp Sajiwa Jail : The great JN escape
  • LS Poll : CAB factor and Manipur
  • Dont trust anyone: Pune police to NE
  • Muhammad Abdur Rahman Khutheibam
  • Yaoshang Fancy Dress : Gallery
  • Urmila Chanam on menstruation myths
  • Meetei Tribe Bears More Tribal Characters
  • Dear Happiness :: Poem
  • MP election issues & non-issues
  • Augment credit flow to farm sector
  • Fresh approach of Sangma
  • Phayeng Koubru Haraoba #3: Gallery
  • TabLlE :: Seireng
  • The Naliya Queen
  • Distress Relief at various districts
  • Bedtime Blues :: Poem
  • Babies who are born deaf
  • The approaching day of redemption
  • Yaoshang Marathon Race: Gallery
  • Abok :: Artwork & an Essay
  • Eyek Tamba :: Learn Manipuri script
  • Yaoshang Pichakari #2: Gallery
  • Utlou incident & of Nupi Khongoinaba
  • Understanding failure & how to face it
  • Responsibilities of voters : 5 years stake
  • Nando escaped from custody is a threat..
  • A New Dawn Awaits Tusom & Somra
  • Yaoshang Cooking competition: Gallery
  • MSAC Literary Meet @Chandigarh : Gallery
  • Lamtagee Thabal @ Pune : Gallery
  • Yaoshang Sports @Keishampat #1 : Gallery
  • Abdur Rahaman : Gopal Sharma Award
  • Thokchom Sanatombi : Sangeetratna
  • AEgi puNsi :: Seireng
  • Nipalsuba Mapok : Shumang Leela
  • Mukna Kangjei #2 : Gallery
  • Sory Wahengbam : eRang Actress Profile
  • Saroi Khangba @Imphal : Gallery
  • Featured Front Page Photo 2019 #1: Gallery
  • Maharaj Kumar Priyabarta Singh : Profile
  • Manipuri Calendar for 2019 : Download
  • List of Restricted Holidays for 2019
  • List of Public Holidays for 2019
  • List of General Holidays for 2019
  • SPONSORED ADS