Source: The Sangai Express / Newmai News Network
Imphal, July 21 2009:
Electrification of un-electrified villages in Tamenglong district in Manipur under RGGVY programme has been finalized and stipulated time for completion of the work is February, 2010, informed Manipur power minister Phungzathang Tonsing in the Manipur legislative assembly today during the question hour.
The power minister was replying to questions raised by Awangbow Newmai, MLA of Tamei assembly constituency, Tamenglong district, as to whether work order for electrification of un-electrified villages in Tamenglong district under RGGVY programme has been finalized, details of villages included in the work programme and stipulated time for completion of work.
It was informed that 79 villages were electrified under RGGVY in Tamenglong district, 45 villages de-electrified, 8 villages un-electrified and 19 were habitation villages.