IFC Minister N Biren replying to MLA S Joy said construction of bored piles and retaining wall at Wangoi section of Imphal Turel (river) has been included in the 2010-11 SPA programme.
The Minister also informed the House that all works related to maintenance of Imphal Barrage are undertaken under the non-plan head and as no budgetary provision had been made in the 2010-11 fiscal there is plan for construction of canal in between Leishangkhong and Loktak Lake point.
N Biren, who also holds the Sports portfolio, stated that 16 work programmes at a total cost of Rs 18 crore are being implemented at the Regional Water Sports Complex, Takmu with MDS and LDA as the implementing agencies.